Diligence · updated 5 November 2026

Nine things a counterparty checks. Five are closed.

Every item below carries a status and a date. Tap any row for what it means and which document sits behind it. Two filings go in December 2026; the campus is fully entitled by Q1 2027.

5 of 9Closed today
Dec 2026Two filings
Q1 2027Fully entitled
5/9Closed
The ledger

Read it in twenty seconds.

Status, date, document. Nothing else.

One contiguous parcel with a 200-foot evergreen buffer, outside the floodplain, with the plant and the halls on the same title. No assemblage risk, no third-party consent in the path.

DocumentParcel deed & option · survey

The Zoning and Planning Board has issued a signed letter confirming data centre use and power plant use on the parcel. Both uses, one document, one jurisdiction.

DocumentBoard letter · 24 June 2026

Use sits under the zoning board's jurisdiction, and there is no township zoning ordinance to amend or rezone against. The approved use is on the record.

DocumentJurisdiction memo · solicitor opinion

An executed tap on a 20-inch transmission pipeline that crosses the parcel. Fuel does not depend on a new lateral, a new right-of-way, or a third-party compressor upgrade.

DocumentTap agreement · February 2026

A 230 kV PENELEC line crosses the property with right-of-way confirmed. It carries the surplus-to-PJM option and station service — it is not in the path of your load.

DocumentRight-of-way exhibit · January 2026

The application is being prepared for submission in December 2026, covering nine LM2500+G4 machines on a minor-source pathway with the modelling already run. Emission inventory and dispersion modelling are complete.

DocumentPre-application record · modelling set

Submitted together with the air permit in December 2026. The site plan set is at 60% with stormwater, grading and the eight hall pads laid out.

DocumentSite plan L-1.1 · 60% set

With both filings in December 2026, the review calendar lands on full entitlement in the first quarter of 2027. There is no township clock and no rezone to wait on — the county review window is the only one.

DocumentEntitlement schedule

Closed-loop cooling with no evaporative towers and zero process water — the design removes the water permit from the critical path entirely. Two fibre carriers are on route with diversity into Scranton and Harrisburg.

DocumentUtility letters · carrier routes

Status as of 5 November 2026 · documents available under NDA

The plan

Eight halls, one plant, everything on the parcel.

Scroll to draw the plan. Toggle the power and gas layers to see what is already at the fence.

PENELEC 230 kV · ON THE PARCEL 412 MW ON-SITE PLANT 9 × LM2500+G4 DC-0140,000 SF · 51.5 MW DC-0240,000 SF · 51.5 MW DC-0340,000 SF · 51.5 MW DC-0440,000 SF · 51.5 MW DC-0540,000 SF · 51.5 MW DC-0640,000 SF · 51.5 MW DC-0740,000 SF · 51.5 MW DC-0840,000 SF · 51.5 MW 20" GAS · ON PROPERTY N 0400 FT
Swipe the plan to pan →
PENELEC 230 kV 20" gas line Hall footprint On-site plant

L-1.1 · preliminary site plan · 8 equal halls · not for construction

Reach

Latency, drawn from the parcel.

Propagation from 41.78°N, 76.50°W. Design model — not a measured SLA.

SCRANTON ALLENTOWN HARRISBURG BUFFALO PHILADELPHIA NEW YORK TORONTO ASHBURN PITTSBURGH CLEVELAND BOSTON CHICAGO
Philadelphia2.53ms
New York2.61ms
Ashburn3.55ms
Pittsburgh3.63ms
Boston5.18ms
Chicago10.41ms

Toggle to the conservative method (1.15 route factor, 5% slack) to match the figures published on the current site.

Calendar

Two filings, then entitlement.

Air permit and land development go in together in December 2026.

June 2026Use confirmed

Board letter for data centre and power plant use.

December 2026Two filings

Air permit and land development, same month.

Q1 2027Fully entitled

Construction-ready, no township clock.

2027First hall live

DC-01 energised from the on-parcel plant.

Data room

Eighty-two documents, organised the way you read them.

Open under a mutual NDA. Request access and we countersign the same day.

01Land14 documents
02Power22 documents
03Permits9 documents
04Engineering31 documents
05Commercial6 documents
Prototype form — nothing is transmitted. Mutual NDA, countersigned same day.